Columbia Gas of Ohio will continue work on their gas main line replacement project

Gasline

Columbia Gas of Ohio will continue work on their gas main line replacement project affecting several city streets. The following is a tentative schedule for the upcoming roadwork:

Monday, March 21, 2022 – Friday, March 25, 2022

Main line installation on Offnere Street from 3rd  Street to 4th  Street. Flaggers will be used to route traffic around work limits on Offnere Street.

Service installation at various locations on 5th  and 6th Streets. Flaggers will be used to route traffic around work limits.

R&R Pipeline, Inc. will be performing the work.

Respectfully,

Nathan Prosch, P.E.

City Engineer

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS